Milestone 05

Connecting the Culm

Develop Business Case and Financial Model

Investment Readiness Toolkit › Milestone 05: Develop Business Case and Financial Model
05
Initial Project Scoping
Identify and Work with Sellers
Baselining and Estimating Ecosystem Services
Identify and Work with Buyers
Develop Business Case and Financial Model
Developing a Governance Structure
Identify and Work with Investors
Establish Legal Contracts and Closing
Community Engagement
Policy and Regulation
05
Initial Project Scoping
Identify and Work with Sellers
Baselining and Estimating Ecosystem Services
Identify and Work with Buyers
Develop Business Case and Financial Model
Developing a Governance Structure
Identify and Work with Investors
Establish Legal Contracts and Closing
Community Engagement
Policy and Regulation

Project Summary

The Connecting the Culm (CtC) Programme is a long-term initiative focused on improving the environmental condition and resilience of the 300 square-kilometres River Culm catchment in Devon. Led by the Blackdown Hills National Landscape and supported by local authorities and agencies, the Project aims to address flooding, drought, water quality, habitat condition, and soil health at a catchment scale.

Using a 25-year Blueprint, CtC is assessing and delivering nature-based solutions (NbS), including soil management measures, riparian planting, and river re-meandering. Modelling indicates these interventions could reduce flood risk for around 200 properties and lower peak flows at key infrastructure by up to 20%.
Since 2018, the project has secured £3 million, £1 million of which has enabled nature-based solutions to be delivered at scale across at least 80 landholdings. CtC has a long-term aim of influencing management across the catchment with a wider £36 million programme.

Milestone 1: Initial Project Scoping

Often the initial task is to understand the site(s) you want to use and the land use change needed for nature restoration or creation. This includes considering the goals of the land managers involved, the vision within the wider catchment or neighbouring area, and whether there are permits or planning consent needed for any proposed changes.

At this stage, you can also conduct a high-level assessment to determine which revenue streams can be generated from ecosystem services , e.g. carbon credits, flood reduction cost savings, or biodiversity units, which will be crucial for identifying buyer interest.

Finally, it is useful to have an idea of the costs of the project and potential grant funding that may be available to support initial development.

Milestone 2: Identify and Work with Sellers

In this Toolkit, sellers are primarily the land managers who own or manage the land on which ecosystem services are generated, including farmers, estate managers and, in some cases, tenants. They are a key stakeholder in any nature-based project, as their long-term stewardship underpins the delivery and permanence of environmental outcomes.

Some projects are led directly by land managers, while others involve third-party project developers who help design projects, secure finance or bring ecosystem services to market. Even in these cases, land managers remain central to project success, and their objectives, risk appetite and priorities should be reflected throughout the development process.

Project developers have generally reported that the activities within this Milestone do not require specialist services. However, if the project developer is not local to the area, it is strongly recommended to partner with local organisations – such as farmer advisory services or eNGOs – to help build relationships and trust.

Milestone 3: Baseline and Estimate Ecosystem Services

At this point, you will have understood the vision for the project and identified a particular ecosystem service or set of interventions to be delivered, and engaged with the land manager(s) alongside this. The next step will be to carry out more detailed detailed analysis – baselining each ecosystem service and quantifying what the project can deliver from the interventions, as well as planning how to monitor and maintain these interventions. You will need to rely heavily on ecological expertise for this Milestone.

At this step, standards, verification and accreditation methods will be also considered in more depth.

Milestone 4: Identify and Work with Buyers

Based on your earlier market analysis in initial project scoping, you will have identified one or more groups of beneficiaries who may be willing to ‘buy’ or pay for the ecosystem service(s) to be created, restored or maintained. Buyers vary – as do their requirements – but at this step, greater buyer engagement is now needed to develop a deal that channels money towards the nature-positive outcomes that your project wants to deliver.

 

 

Project Summary

The Connecting the Culm (CtC) Programme is a long-term initiative focused on improving the environmental condition and resilience of the 300 square-kilometres River Culm catchment in Devon. Led by the Blackdown Hills National Landscape and supported by local authorities and agencies, the Project aims to address flooding, drought, water quality, habitat condition, and soil health at a catchment scale.

Using a 25-year Blueprint, CtC is assessing and delivering nature-based solutions (NbS), including soil management measures, riparian planting, and river re-meandering. Modelling indicates these interventions could reduce flood risk for around 200 properties and lower peak flows at key infrastructure by up to 20%.
Since 2018, the project has secured £3 million, £1 million of which has enabled nature-based solutions to be delivered at scale across at least 80 landholdings. CtC has a long-term aim of influencing management across the catchment with a wider £36 million programme.

Milestone 6: Develop a Governance Structure

A governance structure will inform the way in which the project is run when fully operational and for what purpose. It identifies appropriate decision making processes, who is responsible for what actions, and what controls are in place to make sure that the project is meeting its stated goals, all while abiding by the risk appetite of its engaged stakeholders. The legal entity to host the project will be a key driver in this, and the appropriate choice of entity will be dependent on several factors that are outlined below.

Your governance structure should align with and underpin your business case, as a necessary component of how the project will deliver its environmental outcomes and other strategic targets.

Milestone 7: Identify and Work with Investors

It is important to note that not all projects will need up-front investment, but for those that do, this section provides a framework for thinking around the development of the investment model. This does not constitute financial advice – as the GFI is not licensed to do so. However these considerations are based on the insight offered by project developers and other market stakeholders.

An investor will be a new core stakeholder in your project, and it’s just as important to think of what you require from investors, as much as what they require from you – so that you can build a positive and collaborative relationship with them.

This entails defining the investment ask (in line with the financial model), the strategy for approaching the right investors, and the negotiation of terms that can then be formalised in contract development (Milestone 8).

 

Milestone 8: Establish Legal Contracts and Closing

When all relevant stakeholders have been engaged and their terms of engagement are clarified as much as possible, this is the time to develop the legal contracts and close the deal. This stage is last because legal fees are expensive, and it is generally advised to determine as much as possible in previous stages before starting to draw up contracts in earnest.

Note: The information in this Milestone does not constitute any form of legal advice but instead serves as practical advice on how to manage engagement with lawyers and the process of contract development.

The Green Finance Institute is not a firm of solicitors or connected in any way with the courts. The information and opinions we provide in this section and across the Toolkit do not address your individual requirements and are for informational purposes only. They do not constitute any form of legal advice. We recommend that appropriate legal advice should be taken from a qualified solicitor before taking or refraining from taking any action.

Community Engagement

Community engagement is highly advisable for any project that aims to sell ecosystem services, to ensure fair outcomes for local communities and the long-term success of the project. Project developers can build connections with local stakeholder groups early on to spot both risks and opportunities.

Policy and Regulation

Project developers and enterprises will need to keep a continuous check on how current and future policy may affect the project, and also opportunities for the project to inform policy. The role of private finance for nature across the UK is being encouraged by the UK government and its devolved administrations, and new rules, standards and markets are being developed.

 
Quick Stats
  • Location: Devon, England
  • Size of Land: ~300 km²
  • Site types: small number of large estates, many family farms (some tenanted)
  • Nature Market Focus: Payments for Natural Flood Management (NFM) and associated co-benefits
  • Project partners: Blackdown Hills National Landscape, Environment Agency, Devon County Council, Network Rail, National Highways, Mid Devon District Council
Acknowledgements

With many thanks for their time and insight on this case study:

Tim Youngs, Project Director, Connecting the Culm

Lucy Jefferson, Culm Catchment Officer, Connecting the Culm

 

 

Date published: 29/06/26

Next Milestone

Key takeaways

  • Nature-based Solutions (NbS) treated as infrastructure: interventions (Potential Areas of Improved Resilience – PAIRS) are designed and modelled to deliver measurable flood resilience at Hele railway crossing, a critical ‘pinch’ point on the main rail route to the South West.
  • Two linked elements; a c.£20m Headwaters NbS programme and a c.£16m floodplain reconnection (FLooR3) programme, together cut peak flows at Hele crossing (and other infrastructure and property) by c.20%.
  • Funding blends public agri-environment payments with private payments, with infrastructure asset managers (e.g. Network Rail) as an anchor beneficiary.
  • Delivery is ground-truthed: tested via 30 Farm Investment Plans and PAIRS modelled at ~50% uptake to reflect what farmers will deliver.
  • A Resilience Gain Unit (RGU) approach pays land managers annually for additional water stored (2 hours either side of flood peak) on their land, regardless of whether flooding occurs in any particular year.
  • The model is expandable — unlike fixed grey infrastructure, NbS can be scaled up as climate change intensifies.
  • Liability and governance (covenants, repair fund, insurance) are still being worked through.
  • A £2m proof-of-concept phase is testing the model ahead of wider delivery.

 

Introduction

Connecting the Culm (CtC) is built on the premise that nature-based solutions (NbS) can be treated and financed as infrastructure, when directly linked to the performance of assets at risk. The project reframes catchment management as a system delivering measurable resilience outcomes, rather than purely environmental enhancement.

The Culm catchment provides a clear test case for this premise. Steep headwaters, compacted soils and a confined downstream valley create a fast-responding system where rainfall rapidly becomes runoff, increasing flood risk to hundreds of properties along the river and other critical infrastructure. Local organisations have noted these dynamics are intensifying with climate change.

The consequences are most visible at Hele railway crossing, a critical asset on the main rail line into the South West. Flooding disrupts regional and national connectivity. As Tim Youngs, Project Director for Connecting the Culm and Manager of the Blackdown Hills National Landscape partnership, explains, “when Hele crossing floods, it cuts off the whole of Devon and Cornwall… it’s actually the main arterial rail route to the Southwest.”

Even relatively frequent flood events can close the line for hours, triggering delay penalties and wider network disruption. This establishes a clear need for interventions that improve performance, via reducing flood duration and impact (rather than fully preventing flooding). Disruption costs for Hele have not been disclosed, but weather‑related disruption costs Network Rail an estimated £200-300 million per year[i],

Figure 1. Map of Hele Crossing

 

The Intervention Framework and Financial Model

To address this, CtC has developed a modelling and delivery framework with JBA Consulting, capturing the catchment’s ability to address flooding, tailored by sub-catchment. A defining feature of the approach is the separation of interventions into two complementary strands:

  • Headwaters NbS element – costing £20 million and mainly delivered through traditional agri-environment subsidies across 4,500 hectares.
  • Floodplain Reconnection for Railway Resilience (FLooR3) element- costing £16 million and mainly delivered through Resilience Gain Units and associated co-benefits, secured on 200 hectares of land. At this point, Network Rail is identified as one buyer.
  • The CtC financial model, developed with Terranomics, reflects this dual intervention structure and splits costs, incomes, sensitivities and other financial elements across the two strands.

Overall, the programme requires £36 million across 25 years, with approximately £4 million required for upfront capital works in phase 1. CtC aims for a blended public/ private finance mix (including traditional agri-environment subsidies). This includes a 10% contingency that has been applied across all costs in the model, and an inflation rate of 2%.

The two separate strands of interventions are:

 

Headwaters NbS element

The Headwaters NbS element focuses on slowing water further up the catchment. Interventions include soil management, woodland planting, wetlands and leaky features designed to increase infiltration and reduce rapid runoff.

Initial modelling identified Potential Areas of Improved Resilience (PAIRS), representing theoretical opportunities for intervention. These were tested through 30 Farm Investment Plans developed with local landowners. This process revealed that delivery depends not only on payment levels, but on alignment with existing farm systems. As Youngs explains, “you can throw lots of money at a farmer… but if it doesn’t fit their system, they’re just not going to do it.”

The model was therefore adjusted to assume approximately 50% uptake of interventions across 4,500 hectares. While this reduced theoretical performance at ‘tipping points’, it significantly strengthened delivery realism and ensured that outcomes reflect what can be achieved in practice. ‘Resilience performance’ can be maintained through associated floodplain reconnection work (see below).

Total costs are estimated at approximately £20 million over 25 years. This includes capital works, ongoing land management payments and programme delivery costs such as advisory support and monitoring.

CtC plans to fund the Headwaters interventions primarily through public schemes, particularly Environmental Land Management schemes and the England Woodland Creation Offer. This was decided as feasible due to the wider range of co-benefits associated with these interventions, such as improving soil health and water quality. The CtC team has moderate confidence in the delivery  Payments to landowners will be made on an annual basis for hosting the interventions.

While additional ecosystem services such as carbon and biodiversity uplift are present, carbon finance and payments for Biodiversity Net Gain are not relied upon within the model due to market uncertainty and concerns over maintaining financial additionality. The model therefore uses conservative assumptions and focuses on public funding streams, though the model has been designed with the option of including these, should feasible opportunities be identified.

 

Floodplain Reconnection for Railway Resilience (FLooR3)

The FLooR3 element focuses on downstream processes, namely using floodplain reconnection across 200 hectares of floodplain to temporarily store water and increase surface roughness through vegetation to further slow water flow. As Youngs describes, “what happens at the bottom end of the catchment is about temporarily storing large amounts of water and creating friction, to achieve attenuation”

The financial modelling of this strand was driven by the goal of reducing flooding at Hele railway crossing, which was identified as a hydrological tipping point and –of interest to Network Rail.

Through applying climate adaptation pathway principles and working backwards from this asset (to determine nature based solutions needed to significantly improve resilience), plus applying the latest research, CtC identified the need for additional storage capacity closer to the infrastructure. Targeted floodplain reconnection zones were therefore selected within 15 km upstream of the primary asset at risk, Hele crossing. In total, it is estimated that this nature based storage capacity will provide 88,000m3 of additional water storage during moderate flooding and up to 170,000 m3 during extreme flooding.

The element is estimated to cost approximately £16 million over 25 years, including 52% of funds for upfront capital works, and remaining costs covering payments to landowners, annual operations and maintenance.

As of June 2026, a a CtC resilience calculator has been developed that includes a payment per m3 of modelled additional water storage and further payments for each hectare of ‘roughness of vegetation’ (creating friction of water flow) and biodiversity improvements.

Underpinning these payments is a Resilience Gain Unit (RGU) approach, set out in the calculator, built around the participating floodplain farms. A single RGU unit represents one cubic meter of water (additionally) held on the land during a flood event, within two hours either side of the flood peak. The storage potential of each farm is derived from JBA Consulting’s PAIRS mapping, which identified where scrapes and bunds could be created and their combined capacity. A farm’s modelled storage volume is multiplied by a set per-cubic-meter rate and combined with a separate payment for the ‘roughness’ created on surrounding fields (bechnmarked to agri-environment scheme payments), producing a single annual value. The calculator also benchmarks Biodiversity Net Gain units, alongside monitoring and capital costs.

Payments will be made to farmers, as a lump sum or annual basis. Lucy Jefferson, Senior Culm Catchment Officer at Connecting the Culm, explains that payments are made annually regardless of weather conditions. “It’s a payment rate regardless of whether it rains or not,” she notes, reinforcing the concept of resilience as an ongoing service.

When combined with headwaters interventions, the system delivers significant improvements. Peak flows are reduced by approximately 20% and flood duration is shortened. Although flooding still occurs, the line closes later and reopens earlier. As Youngs notes, “for every hour the line’s shut… Network Rail have to pay fines to the train companies… even reducing flooding by 10 hours per flood event would result in significant savings.”

 

Figure 2. Map of the interventions

 

Upfront Capital and Proof–of–Concept Phase

A key challenge with CtC’s model is the need for upfront capital. (2027 to 2029), primarily for floodplain reconnection.

As a large infrastructure developer and operator, Network Rail is constrained by regulation -including confidence in NbS to reduce flooding – and works according to Control/ Funding Period 5-year cycles. The CtC team explored repayable finance from a third party (such as a bank), but the underlying revenue uncertainty means that more work is needed in this area.

To address this, CtC has adopted a phased delivery approach. A £2 million proof-of-concept phase, to be launched in 2027, is designed to deliver initial interventions, test the payment model and generate performance data. CtC and other project stakeholders hope that this phase will reduce uncertainty and support future investment decisions.

 

Delivery, Liability and Governance

A Community Interest Company (CIC) has been set-up- to act as a financial vehicle- which will manage maintenance, monitoring, reporting and engagement. The CIC acts as a coordinating body and does not capitalise assets, as these remain under the ownership and control of participating land managers.

However, implementing infrastructure-like interventions across third-party land introduces governance challenges. As Youngs highlights, “what happens if a storm blows out half a bund? Who owns it?”

As project development progresses, CTC is exploring solutions including conservation covenants, repair funds and insurance mechanisms to address liability and ensure long-term maintenance.

 

Remaining Questions and Next Steps

Key questions remain regarding liability allocation, long-term maintenance funding and the integration of co-finance without compromising resilience outcomes.

Despite this, the project is progressing through its proof-of-concept phase and continuing engagement with stakeholders. Near-term priorities include refining the payment model, securing longer-term funding commitments and developing governance frameworks to enable delivery at scale.

 

Cover image sourced from National Trust Killerton.